Subject: 20183/ChgOrder2/46B-2/Murray Hills Date: Fri, 22 Oct 1993 09:04:00 -0500 RESOLUTION NO. 20183 A RESOLUTION AUTHORIZING CHANGE ORDER NO. 2, CONTRACT NO. 46B-2, MURRAY HILLS COLLECTION SYSTEM III, WITH MAYSE CONSTRUCTION COMPANY, WHICH CHANGE ORDER INCREASES THE CONTRACT BY THE AMOUNT OF TWENTY-FOUR THOUSAND, TWO HUNDRED FIFTY-THREE AND NO/100 DOLLARS ($24,253.00), FOR A REVISED CONTRACT AMOUNT NOT TO EXCEED ONE MILLION, FORTY-EIGHT THOUSAND, SIXTY-ONE AND 50/100 DOLLARS ($1,048,061.50) AND WHICH INCREASES THE CONTRACT TIME NOT TO EXCEED ONE HUNDRED TWENTY (120) DAYS WITHOUT PRIOR APPROVAL. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF CHATTANOOGA, TENNESSEE, That there be and is hereby authorized Change Order No. 2, Contract No. 46B-2, Murray Hills Collection System III, with Mayse Construction Company, which change order increases the contract by the amount of $24,253.00, for a revised contract amount not to exceed $1,048,061.50 and which increases the contract time not to exceed one hundred twenty (120) days without prior approval. ADOPTED: March 29, 1994 :meb